Year 2015 - 2016
Year 2014 - 2015
Year 2013 - 2014
Year 2012 - 2013



Papers

Electricity

Tariff adjustment


Year 2015 - 2016



LC Paper No.PaperMeeting date
CB(4)351/15-16(01) Administration's paper on public consultation on the future development of the electricity market (Follow-up paper) 23 November 2015
15 December 2015
CB(4)407/15-16(01) Administration's paper on coordinate replies from the two power companies information on the balances of the Fuel Clause Recovery Account as at 31 December 2014, 30 June and 31 December 2015 (Follow-up paper) 15 December 2015
CB(4)306/15-16(01) Extract of draft minutes of meeting of the Panel on Economic Development held on 23 November 2015 15 December 2015
CB(4)305/15-16(08) Paper on annual tariff reviews with the two power companies prepared by the Legislative Council Secretariat (updated background brief) 15 December 2015
CB(4)305/15-16(05) Presentation materials provided by CLP Power Hong Kong Ltd. (power-point presentation materials) 15 December 2015
CB(4)305/15-16(04) Presentation materials provided by the Hongkong Electric Company Ltd. (power-point presentation materials) 15 December 2015
CB(4)370/15-16(01) Speaking note from Managing Director of the Hongkong Electric Company Ltd. (follow-up paper) (Chinese version only) 15 December 2015
CB(4)305/15-16(07) Supplementary information provided by CLP Power Hong Kong Ltd. on 2016 Tariff Review 15 December 2015
CB(4)305/15-16(06) Supplementary information provided by The Hongkong Electric Company Ltd. on 2016 Tariff Review 15 December 2015


Year 2014 - 2015



LC Paper No.PaperMeeting date
CB(4)296/14-15(01) List of follow-up actions arising from the discussion at the meeting on 16 December 2014 16 December 2014
CB(4)296/14-15(02)
• CLP Power Hong Kong Ltd.'s written response on issues related to annual tariff reviews set out in the follow-up list (LC Paper No. CB(4)296/14-15(01))
16 December 2014
CB(4)242/14-15(07) Paper on annual tariff reviews with the two power companies prepared by the Legislative Council Secretariat (background brief) 16 December 2014
CB(4)242/14-15(06) Presentation materials provided by CLP Power Hong Kong Ltd. (PowerPoint Presentation Material) 16 December 2014
CB(4)242/14-15(05) Presentation materials provided by the Hongkong Electric Company Ltd. (PowerPoint Presentation Material) 16 December 2014
CB(4)272/14-15(03) Speaking note of Managing Director of the Hongkong Electric Company Ltd. (follow-up paper) (Chinese version only) 16 December 2014
CB(4)272/14-15(02) Supplementary information provided by CLP Power Hong Kong Ltd. on 2015 Tariff Review 16 December 2014
CB(4)272/14-15(01) Supplementary information provided by The Hongkong Electric Company Ltd. on 2015 Tariff Review 16 December 2014


Year 2013 - 2014



LC Paper No.PaperMeeting date
CB(1)344/13-14(06) Administration's paper on Scheme of Control Agreements with the power companies - interim review in 2013 25 November 2013
CB(1)834/13-14(01) Administration's response on the Scheme of Control Agreements with the two power companies – Interim Review in 2013 (follow-up paper) 25 November 2013
CB(1)333/13-14(01) Letter dated 13 November 2013 from Hon SIN Chung-kai on requesting for information on the two power companies (Chinese version only) 25 November 2013
CB(1)391/13-14(01)
• Administration's response to the letter from Hon SIN Chung-kai on requesting for information on the two power companies as set out in LC Paper No. CB(1)333/13-14(01) (Chinese version only)
22 November 2013*
CB(1)344/13-14(07) Paper on Scheme of Control Agreements with the power companies - interim review in 2013 prepared by the Legislative Council Secretariat (background brief) 25 November 2013
CB(1)419/13-14(03) Speaking note of Managing Director of the CLP Power Hong Kong Limited (follow-up paper) 25 November 2013
CB(1)419/13-14(04) Speaking note of Managing Director of the Hongkong Electric Co., Ltd. (follow-up paper) (Chinese version only) 25 November 2013
CB(1)419/13-14(02) Speaking note of the Secretary for Environment (follow-up paper) (Chinese version only) 25 November 2013
CB(1)419/13-14(05) Submission from the Hong Kong Small & Medium Enterprises General Association (follow-up paper) (Chinese version only) 25 November 2013
CB(1)409/13-14(04) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Federation of Hong Kong Industries (English version only) 25 November 2013
CB(1)409/13-14(03) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Baptist University (English version only) 25 November 2013
CB(1)409/13-14(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Institution of Dining Art (Chinese version only) 25 November 2013
CB(1)409/13-14(05) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Safety Electrical Consulting Limited (Chinese version only) 25 November 2013
CB(1)409/13-14(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Sham Tseng Trade Association Limited (Chinese version only) 25 November 2013
CB(1)409/13-14(06) Supplementary information on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from CLP Power Hong Kong Limited (Chinese version only) 25 November 2013
CB(1)524/13-14(02) Information Paper: Development Plan (2014-2018) of CLP/CAPCO and Annexes CLP-C to CLP-E to the Paper provided by CLP Power Hong Kong Limited 10 December 2013
6 February 2014
ENB CR 1/4576/08 (13) Pt.14
ENB CR 2/4576/08 (13) Pt.10
Legislative Council Brief 2014-18 Development Plan and 2014 Tariff Review of the Two Power Companies 10 December 2013
6 February 2014
CB(1)454/13-14(07) Paper on 2014 - 2018 Development Plans and 2014 Annual tariff reviews with the two power companies prepared by the Legislative Council Secretariat (background brief) 10 December 2013
CB(1)454/13-14(04) Presentation materials provided by CLP Power Hong Kong Ltd. (Powerpoint presentation material) 10 December 2013
6 February 2014
CB(1)454/13-14(05) Presentation materials provided by The Hongkong Electric Company Ltd. (power-point presentation material) 10 December 2013
6 February 2014
CB(1)494/13-14(02) Provision of Information by CLP Power Hong Kong Ltd. for Economic Development Panel of the Legislative Council (Annexes CLP-A and CLP-B) 10 December 2013
6 February 2014
CB(1)494/13-14(01) Provision of Information by The Hongkong Electric Company Limited for Economic Development Panel of the Legislative Council (Annexes HEC-A and HEC-B) 10 December 2013
6 February 2014
CB(1)524/13-14(01) Speaking note of the Secretary for Environment (Chinese version only) 10 December 2013
6 February 2014
CB(1)592/13-14(01) Speaking notes of Managing Director of the CLP Power Hong Kong Limited (follow-up paper) (Chinese version only) 10 December 2013
6 February 2014
CB(1)592/13-14(02) Speaking notes of Managing Director of the Hongkong Electric Co., Ltd. (follow-up paper) (Chinese version only) 10 December 2013
6 February 2014
CB(1)454/13-14(06) Supplementary Information from Power Companies on their Development Plans and Annual Tariff Reviews - Elaboration on the Notes on Confidential Information 10 December 2013
6 February 2014
CB(1)542/13-14(01) Letter dated 11 December 2013 from Hon SIN Chung-kai on requesting for information on the two power companies (Chinese version only) 27 January 2014
6 February 2014
CB(1)556/13-14(01)
• Administration's response to the letter from Hon SIN Chung-kai on requesting for information on the two power companies as set out in LC Paper No. CB(1)542/13-14(01)
27 January 2014
6 February 2014
CB(1)835/13-14(01) Letter dated 27 January 2014 from Hon TANG Ka-piu and Hon WONG Kwok-hing on requesting for information on the two power companies (Chinese version only) 6 February 2014
CB(1)835/13-14(02)
• Administration's response to the letter dated 27 January 2014 from Hon TANG Ka-piu and Hon WONG Kwok-hing on requesting for information on the two power companies as set out in LC Paper No. CB(1)835/13-14(01)
6 February 2014
CB(1)847/13-14(01) Letter dated 28 January 2014 from Hon SIN Chung-kai on requesting for information on 2014-18 Development Plan of the two power companies (Chinese version only) 6 February 2014
CB(1)847/13-14(02)
• Administration's response to the letter dated 28 January 2014 from Hon SIN Chung-kai on requesting for information on 2014-18 Development Plan of the two power companies as set out in LC Paper No. CB(1)847/13-14(01)
6 February 2014
CB(1)792/13-14(01) Paper on 2014-2018 Development Plans and 2014 tariff reviews of the two power companies prepared by the Legislative Council Secretariat (Updated background brief) 6 February 2014
CB(1)869/13-14(01) Presentation materials provided by CLP Power Hong Kong Ltd. (Powerpoint presentation material) 6 February 2014


Year 2012 - 2013



LC Paper No.PaperMeeting date
CB(1)189/12-13(03) Administration's paper on the Scheme of Control Agreements with the two power companies interim review in 2013 26 November 2012
25 February 2013
CB(1)290/12-13(02) Administration's response to the information on steps taken by the two power companies to encourage and assist the private sector in saving energy (follow-up paper) 26 November 2012
CB(1)290/12-13(01) Administration's response to the information regarding the reserve capacity of the two power companies, and the justifications for maintaining the levels of reserve capacity (follow-up paper) 26 November 2012
CB(1)189/12-13(04) Paper on Scheme of Control Agreements with the power companies prepared by the Legislative Council Secretariat (background brief) 26 November 2012
25 February 2013
CB(1)83/12-13(01) Submission on the Scheme of Control Agreements 2013 Mid-term Review and the Annual Electricity Tariff Reviews from Friends of the Earth (HK) dated 19 October 2012 (Chinese version only) 26 November 2012
25 February 2013
CB(1)83/12-13(02) Submission on the Scheme of Control Agreements 2013 Mid-term Review and the Annual Electricity Tariff Reviews from Greenpeace dated 20 October 2012 (Chinese version only) 26 November 2012
25 February 2013
CB(1)169/12-13(01) Submission on the Scheme of Control Agreements 2013 Mid-term Review from a deputation (反核之眾(聯盟)) dated 13 November 2012 (Chinese version only) 26 November 2012
25 February 2013
CB(1)201/12-13(01)
• Administration's response to the submission on the Scheme of Control Agreements 2013 Mid-term Review from a deputation (反核之眾(聯盟)) dated 13 November 2012 as set out in LC Paper No. CB(1)169/12-13(01)
26 November 2012
25 February 2013
CB(1)294/12-13(01) Information from Power Companies on Five-year Development Plans and Annual Tariff Reviews - Elaboration on the Notes on Confidential Information 11 December 2012
8 January 2013
CB(1)297/12-13(02) Information paper : CLP Power's 2013 Tariff Review 11 December 2012
8 January 2013
CB(1)297/12-13(01) Information provided by The Hongkong Electric Company Ltd. to the Panel on Economic Development 11 December 2012
8 January 2013
CB(1)260/12-13(10) Paper on annual tariff reviews with the two power companies prepared by the Legislative Council Secretariat (background brief) 11 December 2012
8 January 2013
CB(1)260/12-13(09) Presentation materials provided by CLP Power Hong Kong Ltd. 11 December 2012
8 January 2013
CB(1)260/12-13(08) Presentation materials provided by The Hongkong Electric Company Ltd. 11 December 2012
8 January 2013
CB(1)378/12-13(01) Administration's response to follow-up questions arising from the meeting on 11 December 2012 8 January 2013
ENB CR 3/4576/05(12) Pt.15 Legislative Council Brief on CLP Power Hong Kong Limited and Castle Peak Power Company Limited - Gas supply infrastructure and gas supply agreement issued by the Environment Bureau 8 January 2013
CB(1)401/12-13(01) Paper on natural gas supply to CAPCO/CLP provided by the CLP Power Hong Kong Limited (power-point presentation material) 8 January 2013
CB(1)400/12-13(01) Submission on 2013 Tariff Reviews with the two power companies from Greenpeace (Chinese version only) 8 January 2013
25 February 2013
CB(1)482/12-13(01)
• Administration and the two power companies' response to the submission from Greenpeace on 2013 Tariff Reviews with the two power companies as set out in LC Paper No. CB(1)400/12-13(01)
8 January 2013
25 February 2013
CB(1)445/12-13(01) Joint letter on the Scheme of Control Agreements 2013 Mid-term Review from Hon SIN Chung-kai, Hon WU Chi-wai and Dr Hon Helena WONG Pik-wan dated 16 January 2013 (Chinese version only) 28 January 2013
CB(1)445/12-13(02) Submission on the Scheme of Control Agreements 2013 Mid-term Review from Friends of the Earth (HK) dated 16 January 2013 (Chinese version only) 28 January 2013
25 February 2013
CB(1)772/12-13(01) Administration's paper on Scheme of Control Agreements with the two power companies - Interim Review in 2013 (follow-up paper) 25 February 2013
CB(1)655/12-13(01) Further submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Mr Frankie CHEUNG Ching-to, Vice-chairman of the Hong Kong Shatin Industry & Commerce Association Ltd (Chinese version only) 25 February 2013
CB(1)583/12-13(04) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from a deputation (國基工程有限公司) (Chinese version only) 25 February 2013
CB(1)626/12-13(07) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Civic Party (Chinese version only) 25 February 2013
CB(1)583/12-13(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from CLP Power Hong Kong Ltd 25 February 2013
CB(1)597/12-13(03) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Consumer Council (English version only) 25 February 2013
CB(1)626/12-13(05) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from DAB (Chinese version only) 25 February 2013
CB(1)583/12-13(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Dashun Policy Research Centre (Chinese version only) 25 February 2013
CB(1)565/12-13(09) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Dr C W TSO, Adjunct Professor, School of Energy and Environment, City University of Hong Kong (English version only) 25 February 2013
CB(1)626/12-13(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Federation of Hong Kong Industries (Chinese version only) 25 February 2013
CB(1)597/12-13(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Friends of the Earth (HK) (Chinese version only) 25 February 2013
CB(1)539/12-13(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Greenpeace (Chinese version only) 25 February 2013
CB(1)539/12-13(03) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from HK Society for the Study of Nuclear Radiation (Chinese version only) 25 February 2013
CB(1)626/12-13(09) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Electrical Contractors' Association Limited (Chinese version only) 25 February 2013
CB(1)583/12-13(03) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Energy Studies Centre, Hong Kong Baptist University (English version only) 25 February 2013
CB(1)626/12-13(08) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Federation of Restaurants & Related Trades (HKFORT) (Chinese version only) 25 February 2013
CB(1)565/12-13(07) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong General Chamber of Commerce (English version only) 25 February 2013
CB(1)626/12-13(03) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Professionals & Senior Executives Association (Chinese version only) 25 February 2013
CB(1)597/12-13(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Hong Kong Shatin Industry & Commerce Association Ltd (Chinese version only) 25 February 2013
CB(1)565/12-13(10) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Mr Eugene FONG Yick-jin (Chinese version only) 25 February 2013
CB(1)571/12-13(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Mr HO Sau-mo (Chinese version only) 25 February 2013
CB(1)565/12-13(08) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Mr YEUNG Wai-sing, Eastern District Councilor (Chinese version only) 25 February 2013
CB(1)626/12-13(10) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from New Territories Association of Societies (Chinese version only) 25 February 2013
CB(1)571/12-13(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from Safety Electrical Consulting Limited (Chinese version only) 25 February 2013
CB(1)626/12-13(06) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from The 30S Group - Environment & Energy Working Group (English version only) 25 February 2013
CB(1)626/12-13(04) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from The Association of Hong Kong Professionals (Chinese version only) 25 February 2013
CB(1)626/12-13(02) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from West Kowloon Environmental Protection Association (Chinese version only) 25 February 2013
CB(1)539/12-13(01) Submission on Scheme of Control Agreements with the two power companies - Interim Review in 2013 from World Green Organisation (English version only) 25 February 2013
CB(1)1261/12-13(01) Submission on the Scheme of Control Agreements with the two power companies from Greenpeace and Friends of the Earth dated 6 June 2013 (Chinese version only) 24 June 2013