For discussion PWSC(97-98)41
on 4 June 1997

ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE

HEAD 708 - CAPITAL SUBVENTIONS AND MAJOR SYSTEMS AND EQUIPMENT
New Subhead Improvement works to voluntary agency camps

    Members are invited to recommend to Finance Committee for approval of a commitment of $129.8 million in money-of-the-day prices for improving fire safety measures in 20 subvented voluntary agency camps.



PROBLEM

Twenty voluntary agency (VA) camps subvented by Government do not comply with the provisions of the Hotel and Guesthouse Accommodation Ordinance (Cap. 349) (the Ordinance), and will have to close down on 1 July 1998 if the necessary improvement works are not carried out.

PROPOSAL

2. On the advice of the Director of Architectural Services (D Arch S), the Secretary for Broadcasting, Culture and Sport proposes to improve the fire services installation and the fire safety conditions of 20 subvented VA camps to enable them to comply with the requirements relating to design, structure, fire precautions and safety set out in the Fire Services Ordinance (Cap 95) and the Buildings Ordinance (Cap 123) at an estimated cost of $129.8 million in money-of-the-day (MOD) prices. A list of these camps is at Enclosure 1.

PROJECT SCOPE AND NATURE

3. The scope of the proposed improvement works comprises -

  1. provision or replacement of fire services installations, including fire alarms, fire extinguishers, fire hydrants and hose reels in all 20 camps;

  2. installation of sprinkler systems in 13 of the camps;

  3. installation of smoke detection systems in all 20 camps;

  4. provision of fire services pumps and water tanks for fire hydrants and hose reels in 18 of the camps;

  5. installation of fire resisting doors and fire shutters and replacement of door locks in all 20 camps;

  6. upgrading of electrical works and installations and provision of emergency lighting to 16 of the camps;

  7. provision of additional or upgrading of existing exit signboxes and directional signs in 19 of the camps;

  8. building of or improvement to switch rooms and dangerous goods stores for kitchen fuel in 19 of the camps;

  9. provision of partition walls, modification of building structures, blocking up of ceiling voids above partition walls and replacement of existing false ceilings by fire-proof ceilings in 18 of the camps; and

  10. other minor miscellaneous works required under the Ordinance for the licensing of the 20 camps (including provision of or improvement to handrails at staircases, replacement of curtains made of fire resistant fabric or treatment of existing curtains with fire retardant paint).

JUSTIFICATION

4. The VA camps provide low-cost accommodation and recreational facilities for members of the public in rural locations, often situated near country parks or in other areas of natural scenic beauty. In 1996-97, some 300 000 holiday-makers boarded at the 20 voluntary agencyVA camps. The premises of these camps do not, however, comply with the conditions imposed by the Ordinance for licensing in respect of their fire services installations and fire safety conditionsOrdinance for licensing. They are currently operating under certificates of exemption issued under the Ordinance for a grace period expiring on 1 July 1998. We need to start the proposed improvement works immediately to enable the camps to be licensed under the Ordinance. Otherwise we risk the closure of these camps which would deprive a large section of the community of popular, affordable and well-run recreational facilities. The respective residence capacity and recent utilisation rates of the 20 camps are shown at Enclosure 2. Subject to approval, we plan to start the proposed improvement works in January 1998 and aim to have this completed before December 1998. Pending the completion of works, we will seek an interim extension of the grace period under the Ordinance.

FINANCIAL IMPLICATIONS

5. D Arch S estimates the capital cost of the proposed improvement works to be $129.8 million in MOD prices (see paragraph 6 below), made up as follows -


$ million


(a) Builders works

38.2


(b) Building services works

51.9


(c) Professional services to be provided by Electrical and Mechanical Services Trading Fund in respect of the building services installation 1

8.3


(d) Consultants’ fees

7.7


(e) Contingencies
(7% of (a) and (b))

6.3


Sub-total

112.4

(at December
1996 prices)

(f) Inflation allowance

17.4
_____

Total

129.8

(in MOD prices)

The estimates for the individual camps are included in Enclosure 1. A breakdown by man-months of the estimated consultants’ fees, and the EMSTF charges are at Enclosure 3.

1 Upon its establishment on 1 August 1996 under the Trading Funds Ordinance, the EMSTF starts charging government departments for design and technical consultancy services for electrical and mechanical installations. The services rendered for this project include carrying out the detailed desighn of the associated electrical and mechanical (E&M) installations. A breakdown of the estimated charges by the EMSTF in terms of staff input is at Enclosure 3

6. Subject to approval, we will phase the expenditure as follows -

Year

$ million
(Dec 1996)

Price
adjustment
factor

$ million
(MOD)

1997 - 98

18.0

1.06750

19.2

1998 - 99

87.4

1.16358

101.7

1999 - 2000

7.0
_____

1.26830

8.9
_____


112.4
_____


129.8
_____

7. We have derived the MOD estimate on the basis of the Government’s forecast of trend labour and construction prices for the period from 1997 to 2000. We will use the existing term contractors of D Arch S to carry out the building works so that they can start on site as soon as possible.

8. The VA camps will absorb any additional recurrent expenses arising fromimplications the proposed improvement works. There are no other recurrent financial implications.

PUBLIC CONSULTATION

9. We consider public consultation unnecessary as the proposed improvement works will be carried out mainly within the existing camp areas.

ENVIRONMENTAL IMPLICATIONS

10. The Director of Environmental Protection conducted an environmental review for the proposed improvement works in December 1996 and concluded that they would have no long-term impact on the environment. During construction, D Arch S will control dust, noise and site run-off nuisances by stipulating mitigation measures in the relevant works contracts.

LAND ACQUISITION

11. The proposed improvement works do not require land acquisition.

BACKGROUND INFORMATION

12. We provide the 20 VA camps a total subvention of $22.24 million in 1997-98. This subvention helps towards meeting part of the operating expenses of the camps, in particular, staff costs, rent and rates, and minor repairs. We also provide funds for the scheduled maintenance and repairs of these camps as and when needed.

Broadcasting, Culture and Sport Branch
June 1997
(JJ185)


Enclosure 1 to PWSC(97-98)41

Estimate of capital cost of improvement works for individual camps

Voluntary Agency

Camp

Amount
$ million

(1) Boys’ and Girls’ Clubs Association (BGCA) of Hong Kong

BGCA Bradbury Camp

6.08

(2) Caritas - Hong Kong

(a) Oi Fai Camp

5.80


(b) Ming Fai Camp

7.83


(c) Siu Tong Youth Camp

5.27

(3) Chinese Young Men’s Christian Association

(a) Lion’s - YMCA Youth Camp

4.19


(b) Wu Kai Sha Youth Village

25.45


(c) Y’s Men Wong Yi Chau Camp

5.14

(4) Hong Kong Award for Young People

Duke of EdinburghAward for Young People Training Camp

5.80

(5) Hong Kong Federation of Youth Groups

(a) Lamma Youth Hostel
(b) Tai Mong Tsai Outdoor Training Centre

1.21
2.97

(6) Hong Kong Girl Guides Association

Yuen Long Recreation Centre

10.53

(7) Hong Kong PHAB Association

Lady MacLehose Pokfulam Kong PHAB Centre

5.40

(8) Hong Kong Playground Association

Silvermine Bay Outdoor Recreation Centre

13.50

(9) Hong Kong Red Cross

Shek Pik Youth Camp

3.91

(10) Salvation Army

(a) Cheung Chau Bradbury Camp

5.80


(b) Ma Wan Youth Camp

1.62

(11) Scout Association of Hong Kong

(a) Pak Sha Wan Sea Activity Centre

3.78


(b) Tai Tam Scout Centre

2.29


(c) Tung Tsz Scout Centre

5.80

(12) Young Women's Christian Association

YWCA Youth Camp

7.43
_____


Total

129.80


Enclosure 2 to PWSC(97-98)41

Capacity and utilisation rate of subvented voluntary agency camps

Voluntary Agency Camps

Residential Capacity


No. of Campers



Day
Camp

Residential Camp
(Res)

Utilisation Rate (Res)
Note

(1) Boys’ and Girls’ Clubs Association of Hong Kong





Bradbury Camp

112

295

20 639

73.71%

(2) Caritas - Hong Kong





(a) Oi Fai Camp

84

1 507

13 020

62.00%

(b) Ming Fai Camp

180

2 140

25 260

56.13%

(c) Siu Tong Youth Camp

60

-

7 630

50.87%

(3) Chinese Young Men’ Christian Association





(a) Lion’s - YMCA Youth Camp

112

-

15 445

55.16%

(b) Wu Kai Sha Youth Village

464

52 959

62 349

53.75%*

(c) Y’s Men Wong Yi Chau Camp

120

1 580

15 386

51.29%

(4) Hong Kong Award for Young People





Duke of EdinburghAward for Young People Training Camp

84

3 956

10 032

47.77%

(5) Hong Kong Federation of Youth Groups





(a) Lamma Youth Hostel

30

562

3 114

41.52%

(b) Tai Mong Tsai Outdoor Training Centre

60

1 345

10 779

71.86%

6) Hong Kong Girl Guides Association





Yuen Long Recreation Centre

48

1 339

6 365

53.04%

(7) Hong Kong PHAB Association





Lady MacLehose Pokfulam Hong Kong HAB Centre

100

12 220

19 146

76.58%

(8) Hong Kong Playground Association





Silvermine Bay Outdoor Recreation Centre

120

-

14 987

49.96%*

(9) Hong Kong Red Cross Shek Pik Youth Camp

50

95

4 360

34.88%*

(10) Salvation Army





(a) Cheung Chau Bradbury Camp

108

-

20 553

76.12%

(b) Ma Wan Youth Camp

40

-

4 945

49.45%

(11) Scout Association of Hong Kong





(a) Pak Sha Wan Sea activity Centre

60

11 374

8 538

56.92%

(b) Tai Tam Scout Centre

80

21 349

16 976

84.88%

(c) Tung Tsz Scout Centre

100

10 179

12 237

48.95%*

(12) Young Women's Christian Association





YWCA Youth Camp

120

-

23 532

78.44%


TOTAL

120 900

315 293

58.66%
(average)

Note : Based on 250 operational days in a year

* Operational days less than 250 in 1996-97 due to closure of camp for renovation. Actual utilisation rate should be higher if the non-operational days are discounted


Enclosure 3 to PWSC(97-98)41

Details of Consultants’ Fees

A breakdown of the estimates of consultants’ fees for service to be rendered during the construction stage is shown below-

Consultants’ staff cost

Grade

Estimated man-months

Average MPS salary point

Multiplier factor

Estimated fee
($ M)

(a)

Survey of the existing layout and conditions of the VA camps

Professional Technical

6
7

40
16

3.0
3.0

1.00
0.39

(b)

Preparation of building plans for licence application submission

Professional
Technical

9
13

40
16

3.0
3.0

1.50
0.73

(c)

Preparation of fire services installation proposal for licence application submission

Professional
Technical

9
13

40
16

3.0
3.0

1.50
0.73

(d)

Making amendments and preparation of re-submission of building and fire services installation proposal pursuant to comments from licensing authority.

Professional
Technical

2
3

40
16

3.0
3.0

0.33
0.17

(e)

Structural assessment of fire services tanks on existing structure

Professional
Technical

3
3

40
16

3.0
3.0

0.50
0.17

(f)

Periodic site visits to monitor compliance with licensing requirements

Professional

4

40

3.0

0.66
__________




Total consultants’ staff cost

7.68
(say, $7.7M)
__________

Notes

  1. A multiplier factor of 3 is applied to the average MPS point to arrive at the full staff costs including the consultants’ overheads and profit, as the staff will be employed in the consultants’ office. (at 1.4.1996, MPS pt. 40 = $55,390 p.m. and MPS pt.16 = $18,595 p.m.)

  2. The figures given above are based on estimates prepared by the Director Of Architectural Services. We will only know the actual man-months and actual fees when we have selected the consultant through the usual competitive lump sum fee bid system.


Details of EMSTF charges

Estimated
man-months
Estimated
Charge
($ million)
(a) Senior Building Services Engineer 122.39
(b) Building Services Engineer18 2.63
(c) Technical Staff403.28
Total8.30

* The EMSTF charges are estimated on the basis of the required professional input which is then calculated based on the average MPS point multiplied by a factor 2.75 to take account of the associated expenses, staff on-cost, overheads and other Trading Fund expenses.


Last Updated on 16 August 1999