For discussion PWSC(97-98)4
on 23 April 1997
ITEM FOR PUBLIC WORKS SUBCOMMITTEE
OF FINANCE COMMITTEE
HEAD 705 - CIVIL ENGINEERING
Civil Engineering - Land development
480CL - Disposal of contaminated mud - management and capping of contaminated mud pit IV
Members are invited to recommend to Finance Committee the upgrading of 480CL to Category A at an estimated cost of $570.1 million in money-of-the-day prices for the management and capping of the fourth contaminated mud pit at East Sha Chau.
PROBLEM
The existing facilities for disposing of contaminated mud from on-going and planned projects will reach full capacity by mid-1997.
PROPOSAL
2. The Director of Civil Engineering, with the support of the Secretary for Planning, Environment and Lands, proposes to upgrade 480CL to Category A at an estimated cost of $570.1 million in money-of-the-day (MOD) prices for the management and capping of a fourth contaminated mud pit (CMP IV) at East Sha Chau.
PROJECT SCOPE AND NATURE
3. The scope of the project comprises -
- bund construction;
- on-site control of mud disposal activities;
- capping works; and
- environmental monitoring during mud disposal operations and for a period of two years following completion of the disposal programme.
JUSTIFICATION
4. Since 1992, we have disposed of contaminated mud in dredged seabed pits at East Sha Chau. To date, we have used three groups of contaminated mud pits, namely CMP I, II and III comprising a total of nine sub-pits as shown on the location plan at Enclosure 1. The last sub-pit of this series, CMP IIId, will be filled up by mid-1997 at which time we will need to make available a new group of seabed sub-pits, namely CMP IV to cater for the disposal of contaminated mud arising from on-going and planned projects. A list of those projects which we have identified will generate contaminated mud requiring disposal between 1997 and 2002 is at Enclosure 2.
5. The implementation of projects at Enclosure 2 will be adversely affected if the contaminated mud disposal facilities are not available in time, that is, by mid-1997. In particular, on-going and planned flood protection works in the New Territories and harbour maintenance dredging works will either come to a halt or not be able to proceed. In the case of on-going projects, the failure to provide contaminated mud disposal facilities may lead to contractual claims against the Government.
6. The design capacity of CMP IV is about 29 million cubic metres, which should meet the projected demand for contaminated mud disposal up to 2002. Unlike CMP I, II & III which were formed by dredging pits in the seabed, we will form CMP IV by using existing seabed borrow pits left empty following the construction of Chek Lap Kok Airport. Such an approach will result in significant cost savings. For optimal control of mud disposal activities, we will sub-divide CMP IV into three sub-pits by constructing a bund between CMP IVa and CMP IVb and enlarging the existing bund between CMP IVb and CMP IVc. We will isolate all deposited contaminated mud from the marine environment by capping the pits with clean sand and uncontaminated mud.
7. As CMP IV will be a multi-user disposal facility, we need to assume on-site control of mud disposal activities to ensure that the contaminated mud is deposited in the correct way and in the correct position.
8. Since 1993, we have monitored the environmental impact of disposal operations in CMPs. We plan to continue such monitoring during the disposal operations at CMP IV and for about two years thereafter. We will engage consultants to undertake this task which will comprise sampling and testing of the water, sediment and marine biota at East Sha Chau.
FINANCIAL IMPLICATIONS
9. We estimate the capital cost of the project to be $570.1 million in MOD prices (see paragraph 10 below), made up as follows -
|
|
$ million
|
(a) Bund construction
|
|
22.4
|
(b) On-site control of mud disposal activities
|
|
31.9
|
(c) Capping works
|
|
180.8
|
(d) Environmental monitoring and audit
|
|
118.7
|
(i) consultants fees
|
61.2
|
|
(ii) sampling and testing
|
57.5
|
|
(e) Contingencies
|
|
35.0
|
|
|
_____
|
Sub-total
(at December 1996 prices)
|
|
388.8
|
(f) Inflation allowance
|
|
181.3
|
|
|
_____
|
Total
(in MOD prices)
|
|
570.1
|
|
|
_____ |
A breakdown by man months of the estimate for consultants fees is at Enclosure 3.
10. Subject to approval, we will phase expenditure as follows -
Year
|
$ million
(Dec 1996)
|
Price
adjustment
factor
|
$ million
(MOD)
|
1997 - 98
|
36.9
|
1.06750
|
39.4
|
1998 - 99
|
42.8
|
1.16358
|
49.8
|
1999 - 00
|
34.0
|
1.26830
|
43.1
|
2000 - 01
|
70.0
|
1.38244
|
96.8
|
2001 - 02
|
78.7
|
1.50686
|
118.6
|
2002 - 03
|
56.4
|
1.64248
|
92.6
|
2003 - 04
|
41.8
|
1.79030
|
74.8
|
2004 - 05
|
28.2
|
1.95143
|
55.0
|
|
_____
|
|
_____
|
|
388.8
|
|
570.1
|
|
_____
|
|
_____ |
11. We have derived the MOD estimate on the basis of the Governments forecasts of trend labour and construction prices for the period 1997 to 2005. We will tender the on-site control of mud disposal activities, bund construction and capping works under standard remeasurement contracts with provision for inflation adjustment because of the uncertainty of the rate at which disposable mud will be received, the seabed conditions and the fact that the duration of the contract period will be greater than 21 months. We will award the environmental monitoring consultancy on a lump-sum basis with provision for inflation adjustment as the contract period will be greater than 12 months.
12. The proposed works will not give rise to any recurrent expenditure.
PUBLIC CONSULTATION
13. The East Sha Chau contaminated mud disposal area, which covers the proposed CMP IV, was authorised under the Foreshore and Seabed (Reclamations) Ordinance in February 1992.
14. We have briefed the Advisory Council on the Environment (ACE) regularly on contaminated mud disposal operations at East Sha Chau since ACEs predecessor, the Environmental Pollution Advisory Committee, endorsed the use of the facility in 1993. On 25 November 1996, we provided ACE with the most recent update on mud disposal operations which included the programme for CMP IV. On 3 March 1997 and 24 March 1997, we presented the findings of the Environmental Impact Assessment (EIA) for CMP IV to the EIA Subcommittee of ACE and ACE respectively. ACE endorsed the EIA on 24 March 1997.
15. On 25 February 1997, we briefed the Legislative Council Panel on Environmental Affairs on mud disposal activities at East Sha Chau and subsequently provided the Panel with additional information concerning site selection and alternative disposal options. The Panel noted the consultants conclusion that there was no evidence of direct or indirect links between contaminated mud disposal at East Sha Chau and the contaminants found in the tissue of Chinese White Dolphins.
16. We consulted the Environmental Improvement and District Development Committee (EIDDC) of the Tuen Mun District Board on 10 January 1997. The Committee expressed concern about the environmental impact of the proposals for CMP IV. On 5 March 1997 officials accompanied Committee members on a site visit to the disposal area. Subsequently, the EIDDC discussed the proposal at a meeting held on 7 March 1997 and the Committee accepted the proposal with reservations, urging the Government to -
- keep the environmental nuisance to a minimum;
- ensure that the operational guidelines would be followed strictly;
- submit reports to the EIDDC regularly; and
- endeavour to restore the concerned seabed area to its original ecological environment and discontinue marine disposal at East Sha Chau after CMP IV is filled up.
17. We presented details of the proposed project to the Islands District Board on 17 February 1997. The Board had no objection to the proposal.
18. We have regularly briefed the Capture Fisheries Subcommittee of the Advisory Committee on Agriculture and Fisheries on the operation of the East Sha Chau contaminated mud disposal facilities and the proposed CMP IV project. The Subcommittee did not object to the proposed project at its meeting on
4 February 1997.
19. We also regularly brief the Marine Mammal Conservation Working Group1 on the progress of contaminated mud disposal operations. The Working Group has no objection to the continuation of disposal activities at East Sha Chau.
ENVIRONMENTAL IMPLICATIONS
20. An intensive environmental monitoring programme for contaminated mud disposal at East Sha Chau covering water, sediment and biota commenced in October 1992 to determine whether the disposal activities would have any adverse environmental impacts. A working group comprising representatives from Environmental Protection Department, Agriculture and Fisheries Department, Civil Engineering Department and New Airport Projects Co-ordination Office is overseeing the environmental monitoring programme. The monitoring results over the past four years have indicated no adverse trends. This indicates that the capped pits have effectively isolated the contaminated mud from the marine environment.
21. In 1995, the London Convention on the Prevention of Marine Pollution by Dumping of Wastes and Other Matters adopted the "Dredged Material Assessment Framework" for managing the dumping of contaminated mud. In 1996, we completed a consultancy study, "Review of Contaminated Mud Disposal Strategy and Status Report on Contaminated Mud Disposal Facility at East Sha Chau", funded under 454CL "Fill Management Study, phase VI - investigation for further fill resources; seabed reinstatement, dredging and marine disposal, environmental and physical studies" to review our existing disposal arrangements in the light of this new and rigorous management framework. The study reaffirmed that the existing contained marine disposal method was environmentally acceptable under the current management and monitoring arrangements, and that East Sha Chau was a suitable, and the preferred, area for contained marine disposal of contaminated mud. Risk assessments, undertaken as part of the study, also indicated that the disposal activities at East Sha Chau did not create public health or ecological risks, including risks to Chinese White Dolphins. We presented the results of this study to ACE in May 1996. Members had no adverse comments.
22. New data on contaminant levels in the body tissue of Chinese White Dolphins became available after May 1996. We then commissioned the consultants to further assess the risk to Chinese White Dolphins. The study, funded under 454CL, concluded that there was no evidence of direct or indirect links between contaminated mud disposal at East Sha Chau and contaminants found in Chinese White Dolphin tissue. On 25 November 1996, we presented the results of this assessment to ACE. Members of ACE had no adverse comment on the findings of the assessment.
23. We completed an EIA for the proposed CMP IV in January 1997. The EIA concluded that disposal of contaminated mud in CMP IV would be environmentally acceptable, and recommended specific controls and an environmental monitoring and audit programme for the operation of CMP IV. As indicated in paragraph 14 above, ACE endorsed the EIA on 24 March 1997.
24. We will implement the operational controls and an environmental monitoring and audit programme, during the operation of CMP IV and for two years thereafter, at an estimated cost of $119 million at December 1996 prices. These steps will ensure that the environmental impacts arising from the proposed project are kept within established guidelines and the assumptions in the EIA. We have included this cost in the project estimate.
LAND ACQUISITION
25. The proposed project does not require land acquisition.
BACKGROUND INFORMATION
26. In May 1993, we upgraded 401CL "Disposal of contaminated mud - dredging, management and capping of contaminated mud pit II" to Category A at $435 million for the dredging, management and capping of CMP II at East Sha Chau.
27. In March 1994, we upgraded 421CL "Disposal of contaminated mud - dredging, management and capping of contaminated mud pit III" to Category A at $151 million for the dredging, management and capping of CMP III at East Sha Chau.
28. We upgraded 480CL to Category B in March 1997.
29. We have substantially completed the detailed design and tender drawings using in-house staff resources. We plan to invite tenders in May 1997 in order that CMP IV will be available to receive the first deposits of contaminated mud by mid-1997.
30. We plan to start the proposed works in July 1997 for completion in mid 2002.
(DD1096)
1 -- This Working Group is chaired by a representative of Director of Agriculture and Fisheries (DAF). Its membership includes officials from relevant government departments and representatives from green groups, fishermen and academics. The Working Group advises DAF on technical and other mattersconcerning conservation of marine mammels.
Enclosure 2 to PWSC(97-98)4
Projects which need contaminated mud disposal facilities from 1997 to 2002
Nature of Works
|
Contract Name (Project Code)
|
Start
|
End
|
Volume of
Contaminated Mud
(Cubic metres)
|
FLOOD PROTECTION/DRAINAGE
|
Yuen Long/Kam Tin Drainage Channels - Stage 1, Phase 2 (43CD)
|
01/96
|
03/98
|
40 000
|
|
Sutlej River Training Stage II
|
01/96
|
11/97
|
5 000
|
|
Village Flood Protection Works for Sha Po Tsuen (71CD)
|
03/96
|
02/98
|
8 000
|
|
Yuen Long/Kam Tin Drainage Channels - Stage II, Phase 1 (22CD)
|
03/96
|
09/98
|
16 000
|
|
Ngau Tam Mei Drainage Channel - Phase 1 (29CD)
|
06/96
|
02/01
|
100 000
|
|
Village Flood Protection Works for San Tin Village
|
12/96
|
05/99
|
44 000
|
|
Shek Wu Hui Development - River Training in Areas 30B & 33 (Part) (87CL)
|
01/97
|
12/98
|
20 000
|
|
Village Flood Protection Works for Ha Mei Shan Tsuen (473CL)
|
03/97
|
03/98
|
10 000
|
|
Village Flood Protection Works for Pok Wai (30CD)
|
11/97
|
07/99
|
23 000
|
|
Yuen Long/Kam Tin Drainage Channels, Stage II, Phase 2 (81CD)
|
01/98
|
12/99
|
60 000
|
|
Indus River Training Stage I (53CD)
|
06/98
|
12/99
|
20 000
|
|
Ngau Tam Mei Drainage Channel - Phase 2 (29CD)
|
02/99
|
02/01
|
40 000
|
|
Yuen Long/Kam Tin Drainage Channels - Stage II, Phase 3 (81CD)
|
02/99
|
02/01
|
40 000
|
|
Village Flood Protection Work for Mai Po Lo Wai, Mai Po San Tsuen (30CD)
|
07/99
|
12/99
|
10 000
|
|
Indus River Training Stage II (53CD)
|
07/99
|
12/99
|
10 000
|
|
Village Flood Protection for Yuen Long/Kam Tin & Ngau Tam Mei Stage II - Remaining Villages
|
08/99
|
12/03
|
4 000
|
|
Village Flood Protection for Yuen Long/Kam Tin & Ngau Tam Mei Stage II - Wang Chau
|
08/99
|
07/01
|
15 000
|
|
Yuen Long/Kam Tin Drainage Channels - Remainder, Phase 4 (22CD)
|
11/99
|
05/02
|
16 000
|
|
Yuen Long Bypass Floodway (70CD)
|
03/01
|
03/04
|
5 000
|
|
Tin Shui Wai Village Flood Protection - Drainage Access Road to Sheung Cheung Wai (227CL)
|
04/01
|
03/02
|
10 000
|
HARBOUR MAINTENANCE
|
Maintenance Dredging at Kwai Chung Container Terminals
|
05/94
|
12/97
|
8 000
|
DREDGING, SEAWALLS & PIERS
|
Dredging of Northern Fairway - Remaining
|
01/96
|
12/98
|
400 000
|
|
Maintenance Dredging at Kwun Tong Public Cargo Working Area
|
05/96
|
12/00
|
6 000
|
|
Dredging in Hung Hom Fairway
|
01/97
|
12/98
|
80 000
|
|
Maintenance Dredging at Sha Tau Kok Typhoon Shelter Anchorage
|
01/97
|
12/97
|
70 000
|
|
Maintenance Dredging at Tuen Mun Typhoon Shelter Area 16 PW
|
01/97
|
12/97
|
4 000
|
|
Maintenance Dredging of Approach to Kwai Chung Container Terminals
|
01/97
|
12/97
|
69 000
|
|
Dredging of Shing Mun River Channel
|
01/98
|
12/00
|
400 000
|
|
Seafrontage Works at Quarry Bay and Cha Kwo Ling (96-97)
|
03/98
|
06/98
|
6 000
|
|
Seafrontage Works at Quarry Bay and Cha Kwo Ling (96-97)
|
03/00
|
06/00
|
6 000
|
|
Seafrontage Works at Quarry Bay and Cha Kwo Ling (96-97)
|
03/02
|
06/02
|
6 000
|
TYPHOON SHELTER/ANCHORAGE
|
Dredging Area of Kellett Bank for Mooring Buoys
|
05/98
|
12/98
|
3 000 000
|
|
Construction of Siu Lam Typhoon Shelter
|
04/99
|
12/99
|
700 000
|
|
Construction of Peng Chau Typhoon Shelter
|
06/99
|
12/01
|
700 000
|
WATER & SEWERAGE
|
Sham Tseng Sewage, Treatment Plant & Submarine Outfall
|
01/96
|
06/98
|
16 000
|
|
Central and Wan Chai East Pumping Station & Screening Plant
|
11/96
|
07/97
|
3 000
|
|
Tung Chung Development - Water Supplies Department Salt Water Pumping Station
|
03/97
|
11/98
|
300 000
|
ROAD WORKS
|
Tai O Creek Improvement Phase I
|
03/96
|
03/98
|
200 000
|
|
Duplicate Tsing Yi South Bridge
|
03/96
|
01/98
|
22 000
|
|
Tai O Development - Northeast Riverwall & Reclamation, Creek Improvement Stage I
|
04/97
|
04/99
|
70 000
|
|
Yuen Long - Tuen Mun Corridor Engineering Works for Ha Mei Sun Tsuen (29CD)
|
07/98
|
09/00
|
10 000
|
|
Widening of Tolo Highway & Traffic Surveillance & Information System
|
12/98
|
12/00
|
300 000
|
|
Yuen Long - Tuen Mun Corridor Engineering Works for Sheung Cheung Wai (213CL)
|
04/00
|
03/02
|
10 000
|
NEW TOWN DEVELOPMENTS
|
Tuen Mun Area 38 Special Industries Development - Reclamation & Construction of Roads & Drain, Stage II
|
04/97
|
01/98
|
189 000
|
|
Tseung Kwan O - Town Centre Extension Reclamation (Stage II)
|
04/97
|
04/00
|
90 000
|
|
Tin Shui Wai Development - Site Formation in Areas 101-108, 109 (Part), 110, 111 (550CL)
|
09/97
|
10/98
|
20 000
|
|
Site Formation for Yuen Long Wholesale Food Market - 455CL
|
02/98
|
10/99
|
40 000
|
|
Tin Shui Wai Development, Drainage Channel & Site Formation Area 109 (Part) & 112-123
|
04/99
|
09/03
|
260 000
|
|
Tseung Kwan O, Phase III - Western Coast Road
|
10/99
|
09/00
|
100 000
|
|
Tsuen Wan Bay Further Reclamation, Area 35, Tsuen Wan
|
03/00
|
03/03
|
3 150 000
|
|
Tseung Kwan O, Phase III - Area 131
|
04/00
|
12/02
|
300 000
|
|
Tseung Kwan O, Phase III - Public Cargo Working Area & Breakwater
|
04/00
|
03/02
|
100 000
|
|
Tung Chung Development - Phase 3
|
01/01
|
12/02
|
300 000
|
OTHERS
|
Pak Shek Kok Reclamation for Public Dumping
|
10/96
|
01/98
|
100 000
|
|
River Trade Terminal
|
01/97
|
12/97
|
200 000
|
|
Tseung Kwan O Port Development Area 137 - Site Completion
|
05/97
|
12/97
|
29 000
|
|
Tseung Kwan O Port Development Area 137 (Fat Tong O) - Remaining Work
|
09/97
|
12/97
|
40 000
|
|
Tuen Mun Port Development (Castle Peak) Phase I
|
04/98
|
02/01
|
3 320 000
|
|
Reclamation Works for District Open Space & GIC Facilities in North Tsing Yi
|
08/98
|
03/99
|
300 000
|
|
West Kowloon Reclamation - Main Works (Remainder) Contract VI (YMG)
|
07/00
|
08/00
|
80 000
|
|
Kowloon Point Development
|
01/01
|
12/05
|
100 000
|
|
Central Reclamation, Phase III
|
01/02
|
12/03
|
210 000
|
|
Lantau Port Development - Advance Reclamation Works
|
-
|
-
|
6 000
|
|
Lantau Port Development - Approach Channel Dredging
|
-
|
-
|
1 500 000
|
|
Lantau Port Development Phase I - Breakwater
|
-
|
-
|
300 000
|
|
Lantau Port Development - Back-up Area for CT10
|
-
|
-
|
40 000
|
|
Container Terminal No. 10 (Dredged Scheme)
|
-
|
-
|
310 000
|
|
Container Terminal No. 11 (Dredged Scheme)
|
-
|
-
|
60 000 |
(DD1096)
Enclosure 3 to PWSC(97-98)4
480CL - Disposal of contaminated mud - management and capping of contaminated mud pit IV
Breakdown of estimates for consultants fees
Consultants staff costs
|
|
Estimated
man
months
|
Average
MPS
salary
point
|
Multiplier
factor
|
Estimated
fee
($ million)
|
Environmental monitoring and audit
|
Professional
Technical
|
276
184
|
42
18
|
3
3
|
49.90
11.32
|
|
|
|
|
_____
|
Total consultants staff costs
|
|
61.22
|
|
|
|
|
_____
|
Out-of-pocket expenses
|
|
|
|
|
|
Sampling and testing
|
|
|
|
|
57.46
|
|
|
|
|
_____
|
Total out-of-pocket expenses
|
|
57.46
|
|
|
|
|
_____ |
Notes
(1) A multiplier factor of 3 is applied to the average MPS point to arrive at the full staff costs including the consultants overheads and profit, as the staff will be employed in the consultants offices. (At 1.4.96, MPS pt. 42 = $60,265 p.m. and MPS pt. 18 = $20,505 p.m.).
(2) Out-of-pocket expenses are the actual costs incurred. The consultants are not entitled to any additional payment for overheads or profit in respect of these items.
(3) The figures given above are only estimates, and the actual man months and actual fees can only be obtained after we have selected the consultants through the usual competitive bidding system.
(DD1096)
Last Updated on 16 August 1999