Year 2020 - 2021

 Paper No.SubjectDecision of
Subcommittee
Decision of
Finance Committee
 
1.PWSC(2020-21)14129KA-Water Supplies Department Headquarters with Hong Kong and Islands Regional Office and Correctional Services Department Headquarters Building in Chai WanEndorsed on
18.11.2020
Approved
(16.12.2020)
FCR(2020-21)74
 
133KA-Drainage Services Department Office Building at Cheung Sha Wan Sewage Pumping StationApproved
(11.12.2020)
FCR(2020-21)72
 
2.PWSC(2020-21)15113ET-Extension of Hong Chi Morninghill School, Tuen MunEndorsed on
18.11.2020
Approved
(11.12.2020)
FCR(2020-21)72
 
3.PWSC(2020-21)16765CL-Development of Anderson Road Quarry site - remaining pedestrian connectivity facilities worksEndorsed on
18.11.2020
Approved
(11.12.2020)
FCR(2020-21)72
 
4.PWSC(2020-21)17353WF-Uprating of Sheung Wong Yi Au fresh water supply systemEndorsed on
18.11.2020
Approved
(11.12.2020)
FCR(2020-21)72
 
371WF-Ngau Tam Mei Water Treatment Works extension
5.PWSC(2020-21)18811CL-Site formation and infrastructure works for public housing developments at Tuen Mun Central – Phase 1Endorsed on
9.12.2020
Approved
(8.1.2021)
FCR(2020-21)80
 
776CL-Site formation and infrastructure works for public housing developments at Kam Tin South, Yuen Long – Phase 1 Approved
(15.1.2021)
FCR(2020-21)81
6.PWSC(2020-21)19399DS-Relocation of Sha Tin Sewage Treatment Works to cavernsEndorsed on
9.12.2020
Approved
(8.1.2021)
FCR(2020-21)78
 
7.PWSC(2020-21)20760CL-Development of Lok Ma Chau Loop - main works package 1Endorsed on
9.12.2020
Approved
(8.1.2021)
FCR(2020-21)79
 
178BF-Fire Station and Ambulance Depot with Departmental Accommodations in Lok Ma Chau Loop
8.PWSC(2020-21)23Capital Works Reserve Fund Block Allocations in 2021-22, and proposals to increase the financial ceilings of the delegated authority for Category D items in the Capital Works Programme, and Block Allocation Subhead on ComputerisationEndorsed on
16.12.2020
Approved
(22.1.2021)
FCR(2020-21)83
 
9.PWSC(2020-21)2176MC-Development of a District Health Centre at Caroline Hill Road SiteEndorsed on
6.1.2021
Approved
(29.1.2021)
FCR(2020-21)85
 
10.PWSC(2020-21)22172CD-Rehabilitation of underground stormwater drainsEndorsed on
6.1.2021
Approved
(29.1.2021)
FCR(2020-21)84
 
11.PWSC(2020-21)24786CL-Tung Chung New Town ExtensionEndorsed on
13.1.2021
Approved
(19.2.2021)
FCR(2020-21)88
 
782CL-Engineering Study on Road P1 (Tai Ho – Sunny Bay Section)
49CG-The District Cooling System for Tung Chung New Town Extension (East)
12.PWSC(2020-21)2551CG-District Cooling System at the Kwu Tung North New Development AreaEndorsed on
13.1.2021
Approved
(5.2.2021)
FCR(2020-21)86
 
13.PWSC(2020-21)2656EF-Centralised General Research Laboratory Complex (Block 2)Endorsed on
20.1.2021
Approved (24.9.2021)
FCR(2021-22)70
 
56EG-Redevelopment of No. 2 University Drive (Building 1)Approved
(26.2.2021)
FCR(2020-21)96
 
64EG-Information Technology Building at University Drive)
14.PWSC(2020-21)27403IO-Fitting-out works for Government facilities associated with Intermodal Transfer Terminal Project at Hong Kong International AirportEndorsed on
20.1.2021
Approved
(19.2.2021)
FCR(2020-21)89
 
15.PWSC(2020-21)2872MC-Enhancement of Public Health Laboratory CentreEndorsed on
20.1.2021
Approved
(19.2.2021)
FCR(2020-21)90
 
16.PWSC(2020-21)29189GK-Construction of a joint-user building for reprovisioning a refuse collection point and setting up a community recycling centre at the junction between Hung Yuen Road and Hung Ping Road, Yuen LongEndorsed on
20.1.2021
Approved
(26.2.2021)
FCR(2020-21)93
 
17.PWSC(2020-21)303QR-Hong Kong-Zhuhai-Macao Bridge – funding support for Main BridgeEndorsed on
27.1.2021
Approved
(19.2.2021)
FCR(2020-21)91
 
18.PWSC(2020-21)31470RO-Lung Tsun Stone Bridge Preservation Corridor at Kai TakEndorsed on
27.1.2021
Approved
(26.3.2021)
FCR(2020-21)95
 
19.PWSC(2020-21)32808CL-Site formation and infrastructure works for public housing developments at Tseung Kwan OEndorsed on
24.2.2021
Approved
(19.3.2021)
FCR(2020-21)99
 
20.PWSC(2020-21)3335NM-Modernisation of Aberdeen Market cum Cooked Food CentreEndorsed on
24.2.2021
Approved
(26.3.2021)
FCR(2020-21)102
 
21.PWSC(2020-21)34332CL-West Kowloon Reclamation―main works (remainder)―footbridge at the junction of Sham Mong Road and Yen Chow Street West in Sham Shui PoEndorsed on
24.2.2021
Approved
(19.3.2021)
FCR(2020-21)97
 
22.PWSC(2020-21)3556WS-Improvement of salt water supply to Tsuen Wan and Kwai ChungEndorsed on
24.2.2021
Approved
(19.3.2021)
FCR(2020-21)98
 
23.PWSC(2020-21)36165DR-West New Territories landfill extensionEndorsed on
24.3.2021
Approved
(10.9.2021)
FCR(2021-22)61
 
24.PWSC(2020-21)37184DR-Refurbishment and upgrading of West Kowloon transfer stationEndorsed on
24.3.2021
Approved
(23.4.2021)
FCR(2021-22)4
 
 185DR-Refurbishment and upgrading of Island West and Island East transfer stations
25.PWSC(2020-21)38365EP-A 36-classroom primary school at Area 9, Tai PoEndorsed on
7.4.2021
Approved
(30.4.2021)
FCR(2021-22)7
 
26.PWSC(2020-21)3942QJ-Youth Hostel Scheme – construction works of the youth hostel project by Tung Wah Group of Hospitals (TWGHs)Endorsed on
7.4.2021
Approved
(30.4.2021)
FCR(2021-22)8
 
 48QJ-Youth Hostel Scheme – construction works by the Hong Kong Girl Guides Association for the youth hostel project in Jordan Approved
(30.4.2021)
FCR(2021-22)8
 
27.PWSC(2021-22)1 365WF-Siu Ho Wan water treatment works extensionEndorsed on
21.4.2021
Approved
(14.5.2021)
FCR(2021-22)10
 
 54WS-Salt water supply to Sha Tin Area 52, Shui Chuen O
 55WS-Reclaimed water supply to Sheung Shui and Fanling
28.PWSC(2021-22)221EM-Development of the Vocational Training Council Aviation and Maritime Education Centre at Tsing YiEndorsed on
21.4.2021
Approved
(14.5.2021)
FCR(2021-22)11
 
29.PWSC(2021-22)3856TH-Flyover from Kwai Tsing Interchange Upramp to Kwai Chung RoadEndorsed on
21.4.2021
Approved
(14.5.2021)
FCR(2021-22)12
 
30.PWSC(2021-22)4810CL-Site formation and infrastructure works for public housing development at Long Bin, Yuen LongEndorsed on
21.4.2021
Approved
(14.5.2021)
FCR(2021-22)13
 
31.PWSC(2021-22)558TF-Improvement works at Kau Sai Village PierEndorsed on
28.4.2021
Approved
(21.5.2021)
FCR(2021-22)14
 
 59TF-Improvement works at Lai Chi Chong Pier
32.PWSC(2021-22)6766TH-Retrofitting of noise barriers on Po Lam Road NorthEndorsed on
28.4.2021
Approved
(21.5.2021)
FCR(2021-22)15
 
 817TH-Retrofitting of noise barriers on Po Ning Road
33.PWSC(2021-22)7417DS-Construction and rehabilitation of trunk sewage rising mains in Yuen LongEndorsed on
28.4.2021
Approved
(21.5.2021)
FCR(2021-22)16
 
 419DS-Construction and rehabilitation of sewage rising mains in Tai Po Kau
 420DS-Construction and rehabilitation of trunk sewage rising mains in Yau Tong
34.PWSC(2021-22)823TP-Public Vehicle Park at Areas 4 and 30 (Site 2), Sheung ShuiEndorsed on
28.4.2021
Approved
(21.5.2021)
FCR(2021-22)19
 
 24TP-Public Vehicle Park at Area 99, Tung Chung
 85TI-Public Transport Interchange at Tung Chung Area 99
35.PWSC(2021-22)987MM-New Acute Hospital at Kai Tak Development AreaEndorsed on
12.5.2021
Approved
(9.7.2021)
FCR(2021-22)47
 
 3MI-Expansion of North District HospitalApproved
(11.6.2021)
FCR(2021-22)32
 114MH-Expansion of Lai King Building in Princess Margaret HospitalApproved
(11.6.2021)
FCR(2021-22)32
 702CL-Kai Tak development - remaining infrastructure works for developments at the former runway and south apronApproved
(9.7.2021)
FCR(2021-22)47
36.PWSC(2021-22)10170TB-Braemar Hill Pedestrian LinkEndorsed on
12.5.2021
Approved
(4.6.2021)
FCR(2021-22)24
 
37.PWSC(2021-22)11184GK-Chai Wan Government Complex and Vehicle DepotEndorsed on
12.5.2021
Approved
(4.6.2021)
FCR(2021-22)25
 
38.PWSC(2021-22)12116MH-The development of Chinese Medicine Hospital in Tseung Kwan OEndorsed on
20.5.2021
Approved
(11.6.2021)
FCR(2021-22)29
 
 1MZ-The establishment of Government Chinese Medicines Testing Institute in Tseung Kwan O
39.PWSC(2021-22)14884TH-Route 11 (section between Yuen Long and North Lantau)Endorsed on
20.5.2021
Approved
(18.6.2021)
FCR(2021-22)33
40.PWSC(2021-22)1561RE-Renovation and improvement project for the Sai Wan Ho Civic CentreEndorsed on
20.5.2021
Approved
(11.6.2021)
FCR(2021-22)30
 
 62RE-Facility upgrading of Tai Po Civic Centre
 63RE-Renovation of Tsuen Wan Public Library
41.PWSC(2021-22)162QE-Restored Landfill Revitalisation Funding Scheme―E-Co Village at Lot B of Tseung Kwan O Stage I Landfill Endorsed on
2.6.2021
Approved
(25.6.2021)
FCR(2021-22)34
42.PWSC(2021-22)1873MC-Health centre and social welfare facilities building in Siu Sai Wan Endorsed on
2.6.2021
Approved
(25.6.2021)
FCR(2021-22)35
43.PWSC(2021-22)19409DS-North East New Territories sewerage system upgrade Endorsed on
2.6.2021
Approved
(25.6.2021)
FCR(2021-22)36
 
355DS-Outlying Islands sewerage, stage 2―Lamma village sewerage phase 2, package 2
353DS-Outlying Islands sewerage, stage 2―extension of sewerage system to other unsewered villages in Mui Wo
44.PWSC(2021-22)2031ED-Conversion to Shatin Public SchoolEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)42
45.PWSC(2021-22)21841CL-Site formation and associated infrastructural works for development of columbarium at Siu Ho Wan on Lantau IslandEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)43
46.PWSC(2021-22)2273JA-Redevelopment of Western Police Married Quarters siteEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)44
47.PWSC(2021-22)23174BF-Construction of fire station-cum-ambulance depot with departmental quarters and facilities in Area 72, Tseung Kwan OEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)45
48.PWSC(2021-22)24356EP-A 30-classroom primary school in Tsuen Wan West Station (TW7) Development, Tsuen WanEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)49
49.PWSC(2021-22)17451RO-Town Park in Area 68, Tseung Kwan OEndorsed on
16.6.2021
Approved
(9.7.2021)
FCR(2021-22)46
474RO-Kwai Chung Park
449RO-Open space at Hung Hom Waterfront
442RO-Open space at Hoi Fan Road, Tai Kok Tsui
50.PWSC(2021-22)2563EF-Renovation of Facilities in Choh-Ming LI Basic Medical Sciences Building (Remaining Works)Endorsed on
30.6.2021
Approved
(16.7.2021)
FCR(2021-22)52
51.PWSC(2021-22)26852CL-First Phase Development of the New Territories North―San Tin / Lok Ma Chau Development NodeEndorsed on
30.6.2021
Approved
(16.7.2021)
FCR(2021-22)54
854CL-Remaining Phase Development of the New Territories North (NTN)―planning and engineering study for NTN New Town and Man Kam To
52.PWSC(2021-22)27 141KA-Expansion of the Legislative Council ComplexEndorsed on
25.8.2021
Approved
(10.9.2021)
FCR(2021-22)63
53.PWSC(2021-22)28 35QW-Revitalisation Scheme – Revitalisation of the Roberts Block, Old Victoria Barracks into Roberts Block Open HeArts CentreEndorsed on
25.8.2021
Approved
(24.9.2021)
FCR(2021-22)64
36QW-Revitalisation Scheme – Revitalisation of the Luen Wo Market into Luen Wo Market – House of Urban and Rural Living
37QW-Revitalisation Scheme – Revitalisation of the Former Lau Fau Shan Police Station into Hong Kong Guide Dogs Academy
54.PWSC(2021-22)29 54QJ-New facilities building of the Hong Kong Sports InstituteEndorsed on
15.9.2021
Approved
(8.10.2021)
FCR(2021-22)72
55.PWSC(2021-22)30 193GK-Kwun Tong Composite Development ProjectEndorsed on
15.9.2021
Approved
(8.10.2021)
FCR(2021-22)75
206TB-Enchancing Connectivity near MTR Kwun Tong Station with Elevated Landscaped Pedestrian Deck
56.PWSC(2021-22)31 355EP-A 30-classroom primary school at Site KT2c, Development at Anderson Road, Kwun TongEndorsed on
17.9.2021
Approved
(8.10.2021)
FCR(2021-22)76
57.PWSC(2021-22)32 363EP-A 24-classroom primary school at Au Pui Wan Street, Fo Tan, Sha TinEndorsed on
17.9.2021
Approved
(8.10.2021)
FCR(2021-22)77
58.PWSC(2021-22)33 873TH-Boardwalk underneath the Island Eastern CorridorEndorsed on
17.9.2021
Approved
(8.10.2021)
FCR(2021-22)78
59.PWSC(2021-22)34 67EG-Construction of a new academic building on an extension site east of No.3 Sassoon RoadEndorsed on
17.9.2021
Approved
(8.10.2021)
FCR(2021-22)73