I. | Progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension(10:45 am - 12:40 pm) | ||
LC Paper No. CB(1)1604/13-14(01)
(issued on 12 June 2014) | - | Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension
| |
LC Paper No. CB(1)1604/13-14(02)
(issued on 13 June 2014) | - | Paper on the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (background brief)
| |
LC Paper No. CB(1)1490/13-14(01)
(issued on 23 May 2014) | - | Joint letter from Hon WU Chi-wai and Hon SIN Chung-kai on the progress update of the construction of the South Island Line (East) (Chinese version only)
| |
LC Papers Nos. CB(1)1529/13-14(01)
(issued on 28 May 2014) and CB(1)1631/13-14(01) (attached) | - | Letter from Hon Michael TIEN Puk-sun to the Administration on the progress of the five new railway projects under construction (Chinese version only) and Administration's response (Chinese version only)
| |
II. | Any other business(12:40 pm - 12:45 pm) |