Year 2015 - 2016
Year 2014 - 2015
Year 2013 - 2014
Year 2012 - 2013



Subcommittee on Matters Relating to Railways

Papers

West Island Line


Year 2015 - 2016



LC Paper No.PaperMeeting date
CB(4)1020/14-15(01) Administration's response to the letter from Dr Hon KWOK Ka-ki on water seepage in MTR HKU Station of the West Island Line as set out in LC Paper No. CB(4)842/14-15(01) 19 May 2015
3 July 2015
4 December 2015
CB(4)1365/14-15(01) Administration's further response to the joint letter from Hon WONG Kwok-hing, Hon TANG Ka-piu and Hon KWOK Wai-keung on the co-ordination of public transport services upon commissioning of the MTR West Island Line as set out in LC Paper Nos. CB(4)394/14-15(01) and CB(4)522/14-15(01) 4 December 2015
CB(4)298/15-16(02) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (as at 30 September 2015) 14 December 2015
CB(4)610/15-16(03) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (as at 31 December 2015) 22 February 2016
CB(4)960/15-16(01) Administration's supplementary information paper on the additional toilet facilities provided at the new concourses at the stations along the Shatin to Central Link and the original and latest estimates of the construction costs of the various on-going railway projects (Follow-up paper) 22 February 2016
CB(4)610/15-16(04) Paper on the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (updated background brief) 22 February 2016
CB(4)1136/15-16(01) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (as at 31 March 2016) 27 June 2016
CB(4)1136/15-16(02) Paper on the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (updated background brief) 27 June 2016


Year 2014 - 2015



LC Paper No.PaperMeeting date
CB(1)204/14-15(01) Administration's paper on progress update and commissioning arrangement of the West Island Line 24 November 2014
CB(1)291/14-15(01) MTR Corporation Limited's paper on progress update of the construction of the West Island Line (power-point presentation material) (Chinese version only) 24 November 2014
CB(1)260/14-15(06) Paper on the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (updated background brief) 24 November 2014
CB(4)596/14-15(02) Administration's paper on progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (information paper) 6 March 2015
CB(4)394/14-15(01) Joint letter dated 20 January 2015 from Hon WONG Kwok-hing, Hon TANG Ka-piu and Hon KWOK Wai-keung on the co-ordination of public transport services upon commissioning of the MTR West Island Line (Chinese version only) 6 March 2015
CB(4)522/14-15(01)
• Administration's response to the joint letter from Hon WONG Kwok-hing, Hon TANG Ka-piu and Hon KWOK Wai-keung on the co-ordination of public transport services upon commissioning of the MTR West Island Line as set out in LC Paper No. CB(4)394/14-15(01) (Chinese version only)
6 March 2015
CB(1)1365/14-15(01)
• Administration's further response to the joint letter from Hon WONG Kwok-hing, Hon TANG Ka-piu and Hon KWOK Wai-keung on the co-ordination of public transport services upon commissioning of the MTR West Island Line as set out in LC Paper Nos. CB(4)394/14-15(01) and CB(4)522/14-15(01)
27 July 2015*
CB(4)954/14-15(05) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension 19 May 2015
CB(4)842/14-15(01) Letter dated 20 April 2015 from Dr Hon KWOK Ka-ki on water seepage in MTR HKU Station of the West Island Line (Chinese version only) 19 May 2015
CB(4)1020/14-15(01)
• Administration's response to the letter from Dr Hon KWOK Ka-ki on water seepage in MTR HKU Station of the West Island Line as set out in LC Paper No. CB(4)842/14-15(01)
19 May 2015
3 July 2015
4 December 2015
CB(4)1052/14-15(02) MTR Corporation Limited's paper on the progress update of the construction of the West Island Line (power-point presentation material) (Chinese version only) 19 May 2015
CB(4)954/14-15(06) Paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (updated background brief) 19 May 2015
CB(4)1412/14-15(01) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (as at 30 June 2015) 18 August 2015*


Year 2013 - 2014



LC Paper No.PaperMeeting date
CB(1)1604/13-14(01) Administration's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension 17 June 2014
CB(4)317/14-15(01) Administration's supplementary information paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (follow-up paper) 17 June 2014
CB(1)1529/13-14(01) Letter dated 27 May 2014 from Hon Michael TIEN Puk-sun on the progress of the five new railway projects under construction (Chinese version only) 17 June 2014
CB(1)1631/13-14(01)
• Administration's response to letter from Hon Michael TIEN Puk-sun on the progress of the five new railway projects under construction as set out in LC Paper No. (Chinese version only)
17 June 2014
CB(1)1635/13-14(01) MTR Corporation Limited's paper on the progress update of the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension (power-point presentation material) 17 June 2014
CB(1)1604/13-14(02) Paper on the construction of the West Island Line, South Island Line (East) and Kwun Tong Line Extension prepared by the Legislative Council Secretariat (background brief) 17 June 2014
CB(1)1750/13-14(02) Submission on the construction of the West Island Line from DAB Central & Western Branch (Chinese version only) 3 July 2014*
CB(4)307/14-15(01) Administration's supplementary information paper on the number of construction personnel short for each of the five new railway projects under construction (follow-up paper) 4 July 2014


Year 2012 - 2013



LC Paper No.PaperMeeting date
CB(1)1421/12-13(05) Administration's paper on coordination of public transport services to tie in with the commissioning of West Island Line and South Island Line (East) 5 July 2013
CB(1)1636/12-13(01) Administration's supplementary information paper on coordination of public transport services to tie in with the commissioning of West Island Line and South Island Line (East) (follow-up paper) 5 July 2013
CB(1)1421/12-13(06) Paper on West Island Line and South Island Line (East) prepared by the Legislative Council Secretariat (background brief) 5 July 2013
CB(1)1473/12-13(02) Submission from Taxi & P.L.B. Concern Group on West Island Line and South Island Line (East) (Chinese version only) 5 July 2013


* Issue date