For discussion PWSC(95-96)84
on 7 February 1996

ITEM FOR PUBLIC WORKS SUBCOMMITTEE
OF FINANCE COMMITTEE

HEAD 707 - NEW TOWNS AND URBAN AREA DEVELOPMENT
Housing - Rural housing improvement*1
21HH - Local public works in the rural New Territories (1992/93 - 1996/97) Programme

Members are invited to recommend to Finance Committee the upgrading of 21HH, entitled “Local public works in the rural New Territories ( 1996/97 Programme)”, to Category A at an estimated cost of $42 million in money-of-the-day prices.



PROBLEM

Some less-developed areas in the New Territories lack basic amenities and infrastructure. There is a need to improve the rural environment in these areas.

PROPOSAL

2. The Director of Home Affairs, with the support of the Secretary for Home Affairs, proposes to upgrade 21HH to Category A at an estimated cost of $42 million in money-of-the-day (MOD) prices for the implementation of the 1996/97 local public works programme.

PROJECT SCOPE AND NATURE

3. The scope of 21HH covers the following projects in the rural New Territories -

  1. footpaths, minor roads, bridges, and car parks;
  2. water pipelines, irrigation channels and standpipes;
  3. stream embankments, drainage systems, seawalls and piers; and
  4. playgrounds and playground equipment, village squares, rain shelters and parks.

4. Details of the works proposed for upgrading are at Enclosure I.

JUSTIFICATION

5. With the rapid increase in population in the New Territories and the consequent urbanisation in areas around new towns, we consider it necessary to improve the quality of life in the less-developed areas. The local public works programme aims at upgrading the living environment in the less developed areas through the provision of improvement works which are small and localised in nature. The Director of Home Affairs is responsible for implementing and monitoring the programme. Having regard to the views of the local district boards and rural committees and the Heung Yee Kuk, we propose to carry out the works specified at Enclosure I in 1996/97.

FINANCIAL IMPLICATIONS

6. We estimate the capital cost of the 1996/97 programme of works to be $42 million in MOD prices (see paragraph 7 below), made up as follows -


$million

(a) Local public works in

(i) Islands

6.1

(ii) Yuen Long

6.0

(iii) Tai Po

4.0

(iv) North

3.8

(v) Sai Kung

3.2

(vi) Tuen Mun

3.1

(vii) Sha Tin

1.7

(viii) Tsuen Wan

1.5

(ix) Kwai Tsing

1.1

(b) Contingencies

3.0

Sub-total
(at December 1994 prices)

33.5

(c) Inflation allowance

8.5

Total
(in MOD prices)

42.0

7. Subject to approval, we will phase expenditure as follows -

Year $ million (Dec 1994) Price
adjustment
factor
$million
(MOD)

1996 - 97

16.5

1.18250

19.5

1997 - 98

14.1

1.30075

18.3

1998 - 99

2.9

1.43083

4.2


33.5


42.0

8. We derive the MOD estimate on the basis of the Government’s forecasts of trend labour and construction prices over the period between 1996 and 1999. We will tender the local public works under fixed-price lump sum contracts because most of the projects are comparatively simple, small sized civil works. The scopes of these works are well-defined and they can be completed within a short time.

9. We estimate the annually recurrent cost to be $2.1 million.

PUBLIC CONSULTATION

10. We consulted nine NT District Boards and two rural committees between October 1995 and January 1996 and they were in support of the proposed projects. Details of the meetings are at Enclosure II.

ENVIRONMENTAL IMPLICATIONS

11. Local public works items are small scale improvement works, each costing less than $2 million. They will improve the rural environment after implementation. For short term impacts during construction, we will implement standard environmental pollution control measures under the relevant contracts to mitigate noise, dust and site run-off impacts.

LAND ACQUISITION

12. Land acquisition and clearance is not necessary for the proposed works.

BACKGROUND INFORMATION

13. In an effort to improve the rural environment in the New Territories, the Rural Planning and Improvement Strategy (RPIS) Monitoring Group recommended in 1990 to implement a second five-year rural improvement programme for the period from 1992/93 to 1996/97. Consequently we included 21HH in Category B in March 1992 for the implementation of local public works (LPW) and urban fringe improvement (UFI) projects. We upgrade the works under the programme to Category A on an annual basis. We revised the scope of 21HH in January 1994 to only cover LPW projects in the rural New Territories; with UFI projects subsumed under the other RPIS minor items. The 1996/97 programme is the final part of the second five-year rural improvement programme.

14. The Director of Home Affairs took over the planning and implementation of minor RPIS items from the Director of Territory Development in October 1994.

15. We schedule the proposed works in the 1996/97 programme to start in June 1996 for completion in March 1999.

1* -- Members' attetion is also drawn to the PWSC paper (95-96)85 which covers similar works. For administrative purposes, we have divided rural improvement works into two types. The works propsed in this paper are minor in scale with each item costing less than $2 million and do not require land resumption. Those works covered by the PWSC paper (95-96)85 are relatively larger in scale with each item costing between $2 million and $15 million, and may involve land resumption.


21HH - Local public works in the rural New Territories (1992/93 - 1996/97) Programme

Proposed project list for the Local public works in the rural New Territories (1996/97 Programme)

Item District Project Title

1.

Islands

Construction of footpath from one hundred steps leading to Peak Road, Cheung Chau

2.

Islands

Construction of footpath at Fa Peng Road, Cheung Chau

3.

Islands

Reconstruction of paving near No. 44 Hillside Road, Cheung Chau

4.

Islands

Construction of footpath at Ha Keng (phase II), South Lantau

5.

Islands

Reconstruction of drainage and footpath at Shui Hau Tsuen, South Lantau

6.

Islands

Construction of footpath near No. 22 San Wai Village, South Lantau

7.

Islands

Construction of footpath at Tong Fuk Village, South Lantau

8.

Islands

Construction of footpath at Lo Uk Village, South Lantau

9.

Islands

Construction of seawall at Cheung Sha Lower Village, South Lantau

10.

Islands

Construction of footpath at Lo Wai Village, South Lantau

11.

Islands

Provision of railing near House No. 23, Po Wah Yuen, North Lamma

12.

Islands

Provision of handrail at footpath between O Tsai and Po Wah Yuen, North Lamma

13.

Islands

Construction of pavilion at Pak Kap Hang, North Lamma

14.

Islands

Construction of paving and drainage system at Sha Po Village, North Lamma

15.

Islands

Provision of safety railing at Lo So Shing, South Lamma

16.

Islands

Reconstruction of drainage system near Tin Hau Temple at Sok Kwu Wan, South Lamma

17.

Islands

Construction of footbridge and embankment at Lo So Shing, South Lamma

18.

Islands

Construction of footbridge at Man Kok Tsui, Mui Wo

19.

Islands

Reconstruction of footbridge at Tung Wan Mei, Mui Wo

20.

Islands

Reconstruction of stream bund at Ma Po Tsuen, Mui Wo

21.

Islands

Construction of footpath leading to beaches near transmitting station at Pak Wan, Peng Chau

22.

Islands

Construction of rainshelter near Tiu Yu Kung Beach, Peng Chau

23.

Islands

Reconstruction of water supply system at San Tau, Tai O

24.

Islands

Reconstruction of seawall and concrete paving in front of village office of Sha Lo Wan, Tai O

25.

Islands

Reconstruction of bund wall at San Tsuen, Tai O

26.

Islands

Reconstruction of bridge deck from Yi O to Shui Lo Cho

27.

Islands

Construction of concrete paving at Ha Ling Pei, Tung Chung

28.

Islands

Construction of footpath at Pai Mei Tsuen, Tung Chung

29.

Islands

Improvement to water supply system at Tung Chung

30.

Islands

Reconstruction of footpath at Nam Che

31.

Kwai Tsing

Construction of footpath at Shek Lei Hang Tsuen, Kwai Chung

32.

Kwai Tsing

Construction of footpath and channel at Kau Wah Keng Village, Kwai Chung

33.

Kwai Tsing

Construction of channel at Ha Shing Mun, Kwai Chung

34.

Kwai Tsing

Construction of railing at Sai Shan, Tsing Yi

35.

Kwai Tsing

Construction of railing at Mui Kong Tsuen, Kwai Chung

36.

Kwai Tsing

Construction of footpath at Liu To Tsuen, Tsing Yi

37.

Kwai Tsing

Construction of footpath at Cheung Hang Tsuen, Kwai Chung

38.

Kwai Tsing

Construction of footpath and channel at Kau Wah Keng San Tsuen, Kwai Chung

39.

Kwai Tsing

Construction of footpath and channel at Mui Kong Tsuen, Kwai Chung

40.

Kwai Tsing

Construction of footpath at Yau Kom Tau Tsuen, Kwai Chung

41.

Kwai Tsing

Construction of footpath and channel at Lutheran Village, Tsing Yi

42.

North

Reconstruction of drainage channel at On Po Village, Stage II, Sheung Shui

43.

North

Reconstruction of van track at Shek Tsai Ling, Kwu Tung, Sheung Shui

44.

North

Improvement to footpath and drainage channel at Kam Tsin, Sheung Shui

45.

North

Improvement to drainage system at Ping Yeung, Ta Ku Ling

46.

North

Construction of passing bay at Muk Wu, Ta Ku Ling

47.

North

Reconstruction of van track at Lin Ma Hang, Sha Tau Kok

48.

North

Improvement of helicopter landing site at Kat O, Sha Tau Kok

49.

North

Construction of channel and footpath at Tan Chuk Hang Lo Wai, Fanling

50.

North

Improvement of van track at Fu Tei Pai, Fanling

51.

North

Construction of carpark at Liu Pok Village, Stage II, Sheung Shui

52.

North

Reconstruction of footpath at Tsiu Keng, Sheung Shui

53.

North

Reconstruction of road at Tsung Yuen, Ho Sheung Heung, Sheung Shui

54.

North

Improvement to footpath at Shui Wai, Wo Keng Shan, Ta Ku Ling

55.

North

Improvement to van track at Li Uk Tsuen, Ta Ku Ling

56.

North

Repair of footpath and drainage at Wang Shan Keuk San Tsuen, Sha Tau Kok

57.

North

Extension of van track at Lin Ma Hang, Sha Tau Kok

58.

North

Construction of van track at Yim Tso Ha, Sha Tau Kok

59.

North

Improvement to footpath and footbridge at Tung Shan Ha, Hok Tau, Fanling

60.

North

Reconstruction of footbridge at Kwan Tei North, Fanling

61.

Sai Kung

Construction of channels at Sun King Terrace

62.

Sai Kung

Construction of footpath and creation of guard rail at Ma Yau Tong

63.

Sai Kung

Reconstruction of footpath and footsteps at Wo Mei Tsuen

64.

Sai Kung

Reconstruction of footpath at Nam Shan Tsuen

65.

Sai Kung

Reconstruction of footpath and surface channel at Shui Bin Tsuen

66.

Sai Kung

Reconstruction of van track at Nam Wai Tsuen

67.

Sai Kung

Construction of footpath at Tan Cheung

68.

Sai Kung

Construction of footpath, footbridge and railing at San Tei Tsuen

69.

Sai Kung

Construction of drainage system and passing bay at Mang Kung Wo Tsuen

70.

Sai Kung

Erection of traffic signs and construction of roads humps, passing place at Chi Fai Path

71.

Sai Kung

Reconstruction of footpath at Wai Sum Tsuen

72.

Sai Kung

Construction of footpath, footsteps and railing at Luk Mei Tsuen

73.

Sai Kung

Reconstruction of pavement near 68 Sai Kung Road

74.

Sai Kung

Construction of drainage channel and footpath at Tai Po Tsai Tsuen

75.

Sai Kung

Construction of drainage channel at Hing Keng Shek Tsuen

76.

Sai Kung

Construction of footpath from Hiram's Highway to Sun On Tsuen

77.

Sai Kung

Construction of drainage channel at Tai Hang Hau

78.

Sai Kung

Construction of carpark at Tin Liu Tsuen

79.

Sai Kung

Reconstruction of van track at Nam Shan San Tsuen

80.

Sai Kung

Reconstruction of steps with hand railing at Pak Shek Wo Tsuen

81.

Sai Kung

Reconstruction of paving at Leung Shuen Wan

82.

Sai Kung

Construction of staircase with hand railing at Tseng Lan Shue

83.

Sai Kung

Construction of footpath at Po Toi O Tsuen

84.

Sai Kung

Construction of drainage channel at Sheung Sze Wan

85.

Sai Kung

Construction of drainage system, staircase and railing at Pak Shek Wo New Village

86.

Sai Kung

Construction of underground and surface drain at 42 Mau Wu Tsai

87.

Sai Kung

Reconstruction of bridge and van track at Heung Chung Tsuen

88.

Sai Kung

Construction of footbridge at Tin Liu Tsuen

89.

Sai Kung

Reconstruction of footpath at Ma Nam Wat

90.

Sai Kung

Construction of drainage channel at Ta Ho Tun Tsuen

91.

Sai Kung

Erection of railing at O Long Tsuen

92.

Sha Tin

Improvement to concrete footpath and drainage at Tai Wai New Village

93.

Sha Tin

Improvement to channel at Tung Lo Wan Village, Tai Wai

94.

Sha Tin

Reconstruction of footbridge and footpath at Lok Lo Ha

95.

Sha Tin

Improvement to slope behind House 2-6 Mau Tso Ngam Village

96.

Sha Tin

Construction of road humps and traffic signs along Kwun Ping Road

97.

Sha Tin

Improvement to roadside slope at Mau Tat Tsuen

98.

Sha Tin

Reconstruction of village notice boards in Sha Tin District

99.

Sha Tin

Improvement to open space near House No. 4 at Kwun Yam Shan Village

100.

Sha Tin

Improvement to slope and provision of railing to the footpath at Ma On Shan Tsuen

101.

Sha Tin

Improvement to footpath leading from Fu Yung Pit to Kwun Yam Shan

102.

Sha Tin

Reconstruction of vehicular bridge at Mau Tso Ngam

103.

Sha Tin

Construction of paving at Shap Yi Wat

104.

Sha Tin

Improvement to footbridge at Pai Tau Tsuen

105.

Tai Po

Construction of concrete paving and drainage channel at Fong Ma Po, Lam Tsuen

106.

Tai Po

Reconstruction of van track at Tong Sheung Tsuen, Lam Tsuen

107.

Tai Po

Reconstruction of concrete paving near Tai Mei Tuk Village Office

108.

Tai Po

Reconstruction of footpath from Pak Tam Road to Chek Keng, Sai Kung North

109.

Tai Po

Improvement to footpath from Tsung Tsai Yuen to Tai Po Kau

110.

Tai Po

Improvement to footpath at Ha Tei Ha Village, Ting Kok

111.

Tai Po

Reconstruction of footbridge at Yuen Leng Village

112.

Tai Po

Construction of footpath and drainage channel at Tai Wo Village

113.

Tai Po

Construction of paving and passing place at Wai Tau Village

114.

Tai Po

Reconstruction of van track at A Shan, Tseng Tau, Tung Tsz

115.

Tai Po

Reconstruction of drainage channel and footpath at Tong Sheung Tsuen, Lam Tsuen

116.

Tai Po

Reconstruction of van track at Yung Shu O, Sai Kung North

117.

Tai Po

Reconstruction of footpath at Sheung Tin Liu Ha Village, Lam Tsuen

118.

Tai Po

Reconstruction of footpath at Wai Tau Village

119.

Tai Po

Construction of van track at Wong Chuk Yeung, Sai Kung North

120.

Tsuen Wan

Construction of fender wall at Muk Min Ha Village

121.

Tsuen Wan

Construction of footpath at San Po Tsui, Tai Chuen, Lantau

122.

Tsuen Wan

Construction of channel at Pai Min Kok Village

123.

Tsuen Wan

Construction of footpath and railing at Pai Min Kok Village

124.

Tsuen Wan

Construction of communal letter boxes at Pai Min Kok Village

125.

Tsuen Wan

Construction of channel near Chung Kee Store, Lo Wai

126.

Tsuen Wan

Reconstruction of Tsing Lung Tau pier sign board

127.

Tsuen Wan

Erection of Government notice board at Hoi Pa San Tsuen

128.

Tsuen Wan

Construction of van track at Ngon Tong, Chuen Lung

129.

Tsuen Wan

Reconstruction of van track behind West Monastery

130.

Tuen Mun

Construction of drainage channel between Kei Lun Wai and Siu Hang Tsuen

131.

Tuen Mun

Construction of rainshelter and van track at Lung Kwu Tan Tsuen

132.

Tuen Mun

Reconstruction of road at Lo Tsing Shan, So Kwun Wat

133.

Tuen Mun

Construction of footpath at Fu Tei Ha Tsuen

134.

Tuen Mun

Reconstruction of road at Tsz Tin Tsuen

135.

Tuen Mun

Construction of drainage channel at Ching Uk Tsuen, So Kwun Wat

136.

Tuen Mun

Reconstruction of village lane and paving at Lam Tei San Tsuen

137.

Yuen Long

Reconstruction of drainage and footpath at Nga Yiu Tau Tsuen, Shap Pat Heung

138.

Yuen Long

Reconstruction of paving and footpath at Sai Pin Wai Tsuen, Shap Pat Heung

139.

Yuen Long

Reconstruction of drainage and footpath at Yeung Uk Tsuen ,Wang Chau, Ping Shan

140.

Yuen Long

Construction of access road at Mai Po Lung Tsuen, San Tin

141.

Yuen Long

Improvement to drainage channel and footpath at Tan Kwai Tsuen, Ping Shan

142.

Yuen Long

Reconstruction of van track and drainage at Lai Uk Tsuen, Pat Heung

143.

Yuen Long

Improvement to drainage system and van track at Shung Ching San Tsuen, Shap Pat Heung

144.

Yuen Long

Construction of drainage channel and van track at Yeung Uk Tsuen, Shap Pat Heung


Public Consultation for the Implementation of Local Public Works Programme 1996-97

District Date Mode of consultation Remarks

Islands

30 December 1995

District Board
circulation of papers

Project items were supported.

Kwai Tsing

26 October 1995

District Board meeting

Project items were supported.

North

14 November 1995

District Board meeting

Project items were supported.

Sai Kung

9 January 1996

District Board meeting

Project items were supported.

Sha Tin

24 November 1995

Rural Committee meeting

Project items were supported.


5 December 1995

District Board meeting

Project items were supported.

Tai Po

10 November 1995

Rural Committee circulation of papers

No objections to projects.


24 October 1995

District Board meeting

No objections to projects.

Tsuen Wan

28 November 1995

District Board meeting

Project items were supported.

Tuen Mun

16 November 1995

District Board meeting

Project items were supported.

Yuen Long

24 November 1995

District Board meeting

Project items were supported.


Last Updated on 8 December 1998