For discussion PWSC(97-98)13
on 9 May 1997
ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE
HEAD 704 - DRAINAGE
Civil Engineering - Drainage and erosion protection
55CD - Territorial land drainage and flood control strategy study, phase III
Members are invited to recommend to Finance Committee the upgrading of 55CD, retitled "Drainage master plan study in the Northern New Territories" to Category A at an estimated cost of $37.3 million in money-of-the-day prices.
PROBLEM
The Northern New Territories is susceptible to serious and frequent flooding due to the inadequacies of the tributaries, local drainage systems and the main river channels in the area.
PROPOSAL
2. The Director of Drainage Services, with the support of the Secretary for Planning, Environment and Lands, proposes to upgrade 55CD to Category A at an estimated cost of $37.3 million in money-of-the-day (MOD) prices to undertake a drainage master plan study in the Northern New Territories.
PROJECT SCOPE AND NATURE
3. The drainage master plan study in the Northern New Territories covers the catchments including San Tin, Indus and Ganges. The boundary of the study area is shown at Enclosure 1. The scope of the project comprises the following -
- reviewing and assessing the conditions and inadequacies of the existing tributaries and local drainage systems;
- preparing a computerised asset inventory and developing an asset management system for the drainage system to facilitate future system maintenance and development appraisal;
- recommending improvement measures for the tributaries and local drainage systems to meet current standards and future needs;
- carrying out an environmental review for the recommended improvement measures; and
- developing a prioritised implementation programme of works based on a cost-benefit analysis of the recommended improvement measures.
JUSTIFICATION
4. We completed project 52CD "Territorial land drainage and flood control strategy study, phase II - consultants fees and investigation" in August 1993. The study shows that the drainage systems in the Northern New Territories , which comprise mainly river channels and stream courses, are inadequate to cope with the increased stormwater flow due to extensive land development. The area has become susceptible to frequent and serious flooding during rainstorm seasons, causing damage and economic loss.
5. The study recommends the implementation of a number of major improvements to the main river channels and the commissioning of drainage master plan studies. The former will improve the condition of main river channels and water courses, while the latter will look into the inadequacies of tributaries and local drainage systems.
6. Improvement works to the main river channels are now at either planning or detailed design stage. To supplement the works, we propose to conduct a series of survey works and a drainage master plan study under 55CD to investigate into the local drainage problems, develop cost-effective measures to tackle the problems, and develop an asset inventory and an asset management system for the efficient management of the improved drainage systems as well as forward planning of extensions to the systems.
7. The Director of Drainage Services proposes to engage consultants to carry out the study because of insufficient in-house staff resources.
FINANCIAL IMPLICATIONS
8. We estimate the cost of the proposed study to be $37.3 million in MOD prices (see paragraph 9 below) made up as follows -
|
|
$ million
|
|
---|
(a) Surveys
|
|
9.7
|
|
(i) flow/rainfall survey
| |
6.5
|
|
|
(ii) manhole survey
|
| 0.5
|
|
|
(iii) CCTV survey
|
| 0.5
|
|
|
(iv) topographical survey
|
| 2.2
|
|
|
(b) Consultants fees for
|
| 18.6
|
|
(i) supervising survey work
|
| 1.0
|
|
|
(ii) data collection, asset inventory taking, hydrological/hydraulic model building and asset management system development
| |
4.7
|
|
|
(iii) examining conditions and assessing performance of existing system
|
| 3.1
|
|
|
(iv) developing cost-effective options
and a prioritised implementation programme
|
| 9.4
|
|
|
(v) conducting an environmental
review
|
| 0.4
|
|
|
(c) Contingencies
|
|
2.5
|
|
|
|
_____
|
|
Sub-total
|
|
30.8
|
(at December
1996 prices) |
(d) Inflation allowance
|
|
6.5
|
|
|
|
_____
|
|
Total
|
|
37.3
|
(in MOD prices) |
|
|
_____
|
|
A breakdown by man months of the estimate for consultants fees is at Enclosure 2.
9. Subject to approval, we will phase expenditure as follows -
Year
|
$ million
(Dec 1996)
|
Price
adjustment
factor
|
$ million
(MOD)
|
---|
1997 - 98
|
3.2
|
1.06750
|
3.4 |
1998 - 99
|
14.0
|
1.16358
|
16.3 |
1999 - 2000
|
10.8
|
1.26830
|
13.7 |
2000 - 01
|
2.8
|
1.38244
|
3.9 |
|
_____
|
|
_____ |
|
30.8
|
|
37.3 |
|
_____
|
|
_____ |
10. We have derived the MOD estimate on the basis of Governments forecast of trend labour and construction prices for the period 1997 to 2001. We will tender the proposed consultancy on a lump-sum basis with provision for inflation adjustment as the project duration will be ismore than 12 months. The consultants will in turn appoint contractors for the survey work on remeasurement basis through a tendering process. The consultants will adopt this form of contract as they cannot determine in advance the exact extent of the survey work required.
11. This projectThe proposed consultancy will not give rise to any recurrent expenditure.
PUBLIC CONSULTATION
12. This is a feasibility study and public consultation is not necessary at this stage. However, we will consult the public regarding the acceptability of the consultantss recommendations.
ENVIRONMENTAL IMPLICATIONS
13. The study will include an environmental review on the recommended drainage improvement works. The proposed study itself will not cause any adverse environmental impacts.
LAND ACQUISITION
14. The proposed study does not require land acquisition. The consultants will examine the requirement for land to carry out future improvements.
Background INFORMATION
15. We upgraded 55CD to Category B in April 1994. The whole project includes a sedimentation study and two drainage master plan studies in the Northern and North-western New Territories.
16. In November 1994, we upgraded the sedimentation study of 55CD to Category A as 68CD "Territorial land drainage and flood control strategy study phase III, sedimentation study - consultants fees and investigation". The study started in January 1995 for completion in June 1997.
17. In January 1996, we upgraded the drainage master plan study in the North-western New Territories of 55CD to Category A as 83CD "Yuen Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai drainage master plan study". The study started in January 1996 for completion in January 1998.
18. The proposed drainage master plan study is the remaining works under 55CD. We planschedule to commence the drainage master plan study proposed in this paper in October 1997 for completion in June 1999. Upon the completion of this study, we will start the detailed design in mid-2000 and start the construction of the major improvement works in early 2002 for completion in late 2005.
19. The proposed study is the fifth of the seven drainage master plan studies we plan to conduct in the Territory. The first one was 83CD as mentioned in paragraph 17 above. We also upgraded 75CD "Stormwater drainage master plan study in northern Hong Kong Island", 76CD "Stormwater drainage master plan study in Tsuen Wan, Kwai Chung and Tsing Yi" and 78CD "Stormwater drainage master plan study in Tuen Mun and Sham Tseng" to Category A in May 1996, July 1996 and January 1997 respectively. Enclosure 3 shows the study boundaries and the planned programme of the seven drainage master plan studies.
Planning, Environment and Lands Branch
April 1997
(DD1102)
Enclosure 2 to PWSC(97-98)13
55CD - Territorial land drainage and flood control strategy study phase III
Breakdown of estimate for consultants fees -
Consultants staff costs
|
|
Estimated
man
months
|
Average
MPS
salary
point
|
Multiplier
factor
|
Estimated
fee
($ million)
|
---|
(a) Supervising survey
|
Professional
Technical
|
4
6
|
40
16
|
3
3
|
0.66
0.33 |
|
(b) Data collection, asset inventory taking, hydrological/hydraulic model building and asset management system development
|
Professional Technical
|
15
40
|
40
16
|
3
3
|
2.49
2.23 |
(c) Examining conditions and assessing performance of existing system
|
Professional Technical
|
15
10
|
40
16
|
3
3
|
2.49
0.56 |
(d) Developing cost-effective options
and a prioritised implementation programme
|
Professional Technical
|
40
50
|
40
16
|
3
3
|
6.65
2.79 |
(e) Conducting an environmental
review
|
Professional Technical
|
2
2
|
40
16
|
3
3
|
0.33
0.11 |
|
|
|
|
_____ |
Total consultants staff costs
|
|
|
|
18.64 |
|
|
|
|
_____ |
Out-of-pocket expenses
|
|
|
|
|
(a) Flow/rainfall survey
|
|
|
|
6.50 |
(b) Manhole survey
|
|
|
|
0.50 |
(c) CCTV survey
|
|
|
|
0.50 |
(d) Topographical survey
|
|
|
|
2.20 |
|
|
|
|
_____ |
Total out-of-pocket expenses
|
|
|
|
9.70 |
|
|
|
|
_____ |
Notes :
- A multiplier factor of 3 is applied to the average MPS point to arrive at the full staff costs including the consultants overheads and profit, as the staff will be employed in the consultants offices. (At 1.4.96, MPS pt. 40 = $55,390 p.m. and MPS pt. 16 = $18,595 p.m.)
- Out-of-pocket expenses are the actual costs incurred. The consultants are not entitled to any additional payment for overheads or profit in respect of these items.
- The figures given above are based on estimates prepared by the Director of Drainage Services. We will only know the actual man months and actual fees when we have selected the consultants through the usual competitive lump- sum fee bid system.
(DD1102)
Last Updated on 16 August 1999